Client: Retail Unit, Darkhorse, London
Interior Screed Group Ltd completed the floor screeds into a new Darkhorse Restaurant in London. The scheme comprised of installing an ultra-high strength floor screed together with accompanying high-grade insulation.
Scope of Work
- Client: Darkhorse, Retail Unit, London
- Floor Area: 321m²+
- Installation Duration: 5 days
- Materials Used: Tarmac Ultra-Pro Screed C40 | 1200 Guage DPM | 500g VCL | 20mm External Perimeter
Contracted by a returning customer, we were asked to install high strength floor screeding and specialist insulation boards. The project is Darkhorse’s first new restaurant kicking off plans to grow its own restaurant estate.
Project Highlights
Floor screeding commenced following consultation with the client and their design team. Interior Screed Group were then instructed to install to the ground floor, 1200g damp proof membrane with a 500g separating layer together with an 85mm thick C40 ultra-rapid drying fibre reinforced floor screed.
Utilising sand and cement floor screed we provided the contractor with the flexibility to to create micro falls therefore enabling us to easily marry up shop and rear entrance thresholds ensuring final floor finishes fitted perfectly.
Sand and Cement Screed Benefits
- Suitable for wet underfloor heating systems
- Does not require any laitance removal
- Impact and abrasion resistant throughout your build
- Able to form falls to marry up existing entrances & thresholds
- Time consuming tanking/taping of VCL membrane not required
- Reduced risk of shrinking and cracking compared to liquid screed
- Moisture ingress tolerant once initially cured
- Not as susceptible to temperature changes during the curing period